The optimization study aims to improve the NPV, IRR and unit cash cost OPEX by providing improvements to project planning, mine scheduling and a more detailed...
The Feasibility Study planning for Blötberget from 2019 was thorough and in principle well done. WCPL finalized an Activity-Based Costing (ABC) model...
2020-08-20 15:00 Interim Report January - June 2020 Regulatory MAR
A more in-depth evaluation of the project in Blötberget and the market continues to look promising, despite the pandemic Project work The...
Nordic Iron Ore AB has in 2018 issued convertible debentures to Copperstone Resources with a due date 2020-06-11. The company is entitled to request conversion...
2020-05-20 08:30 Interim Report January - March 2020 Regulatory MAR
A turbulent Q1 2020 offered up more drama than anyone could have predicted. The exception was the market for iron ore, which stayed surprisingly...
With the DFS completed last year as a starting point, technical experts from WCPL will model and analyze the complete value chain for the project. Using...
The English translation of our annual report for 2019 can be downloaded from our web page. For further information please contact: Lennart Eliasson Managing...
Nordic Iron Ore's involvement in the Smart Exploration program begins to generate benefits for the company by improving knowledge of both geological...
On February 20th, 2019, the Swedish Mining Inspectorate granted Nordic Iron Ore's application for an exploration permit for "Blötberget...
2020-02-20 08:00 Year-end Report January - December 2019 Regulatory MAR
A positive and eventful year for Nordic Iron Ore In 2019, Nordic Iron Ore progressed from strength to strength. The biggest - and most important...